Upon receiving the investor’s request
the consolidated construction procedures are conducted in the following phases:
- Issuing the location conditions for the cadastre parcel suitable for construction – from the day of obtaining all special conditions, permits and other documents –> no later than 5 working days
- Issuing the construction permit – from the day of the submission of the request –> no later than 5 working days
Upon receiving the application:
Based on registering the construction work, issuing the verification for receiving the applicationwithout delay, provided that the complete documentation has been submitted.
– Registering the construction works to receive acceptance/rejection –> 5 working days
– Subsequently, submitting the request for infrastructure installations –> 3 working days
Issuing the occupancy permit, upon receiving the submission of the request –> no later than 5 working days
Issuing the final approval upon receiving the submission of the request –> no later than 5 working days
In total: 28 working days